Nashville International Airport Begins Concourse A Reconstruction

9/23/2025, 8:59:40 PM

Closure of Concourse A

Nashville International Airport (BNA) is set to close its existing Concourse A on September 24, 2025, as part of its expansion program known as New Horizon. This closure was moved up from the originally scheduled date of October 3, following an announcement made by the airport on September 17. The airport expressed gratitude to its airline partners, concessions, and contractors for their efforts in expediting the closure to facilitate immediate demolition. The new Concourse A is expected to open in July 2028 and will feature 16 gates, two moving walkways, and both indoor and outdoor passenger spaces, making it the largest concourse at BNA.

Background of the New Horizon Expansion

The New Horizon project represents a significant $3 billion investment in the growth and modernization of Nashville International Airport. Prior to the closure of Concourse A, the airport completed the expansion of Concourse D in July 2025, which added five new gates along with new dining and shopping options, including the airport's first outdoor terrace. The expansion aims to enhance passenger experience and accommodate increasing air traffic.

Impact on Local Infrastructure

The closure and subsequent reconstruction of Concourse A are expected to have implications for airport operations and local traffic patterns. The existing concourse has been a notable feature of the airport, and its demolition will mark the end of the recognizable BNA Carpet pattern, which has gained a following on social media. As the airport undergoes these changes, it aims to maintain service continuity and minimize disruption for travelers.

Official Statements & Responses

BNA officials have emphasized the importance of the New Horizon project in meeting future travel demands. They stated, “Thank you to our airline partners, concessions and contractors for working diligently with our staff to expedite the closure so that demolition can begin as soon as possible.” This sentiment reflects the collaborative effort involved in the expansion initiative.

Criticism & Opposition

While the expansion is largely viewed positively, some local residents have expressed concerns regarding potential disruptions during the construction phase. Issues such as increased traffic congestion and noise pollution have been raised, although specific opposition has not been formally documented.

What's Next

As the demolition of Concourse A begins, the airport will focus on the construction of the new facility, with a projected completion date set for July 2028. The airport plans to keep the public informed about progress and any changes to operational procedures during the reconstruction phase.

Verbatim Quotes

  • “Thank you to our airline partners, concessions and contractors for working diligently with our staff to expedite the closure so that demolition can begin as soon as possible,” — BNA Official
  • “The Concourse A Reconstruction is part of New Horizon, the current growth and expansion plan at BNA®.” — BNA Official

This comprehensive approach to the reconstruction of Concourse A is part of Nashville International Airport's broader strategy to enhance its facilities and services in response to growing passenger demands.