Victoria Abandons Shore Power Plan Amid Soaring Costs
10/28/2025
50 8
1 of 1
Story summary
- The Greater Victoria Harbour Authority abandoned shore power plans at Ogden Point due to rising costs, despite $31.5 million in funding.
- The estimated cost climbed from $25 million to nearly $100 million, making the project financially unfeasible.
- The plan would have let cruise ships plug into clean electricity and reduce greenhouse gas emissions.
- Local residents expressed disappointment as oil-fired generators continue to pollute the area.