Data Centers Delayed
- The study found 16 data center projects totaling $64 billion faced delays due to local opposition.
- In Arizona, Tract withdrew a $14 billion project after failing to secure rezoning; in Virginia, 42 activist groups opposed developments.
- From March to June 2025, $98 billion in projects were blocked or delayed, highlighting rising local resistance to data centers amid scrutiny of energy costs.