Georgia Power's Load Project Pipeline Drops 6 GW

11/26/2025

44 7 Full Breakdown

1 of 1

Story summary
  • Georgia Power's large load project pipeline decreased by 6 GW from Q2 to Q3 2025, totaling 50.9 GW.
  • Although 6.8 GW of new projects entered, 14.3 GW exited, raising concerns about demand overestimation.
  • The utility reported 28 commitments from large load customers, totaling 11 GW, but PSC staff warned that most new generation plans lack executed contracts.
  • Since the 2023 Integrated Resource Plan Update, 33 data center projects, accounting for 11,332 MW, have been removed from the pipeline.