Overview of the Incident

On December 20, 2025, a significant power outage struck San Francisco, affecting approximately 130,000 customers, or about one-third of the city. The outage began around 1:00 p.m. and was primarily linked to a fire at a Pacific Gas and Electric Company (PG&E) substation located at 8th and Mission streets. The fire was reported to be under control by 4:24 p.m., but the cause remains under investigation. As of Sunday afternoon, about 13,000 customers were still without power, with full restoration expected by 2:00 p.m. on Monday.

Impact on Daily Life

The outage caused widespread disruptions, particularly on one of the busiest shopping days of the year, just days before Christmas. Many businesses, including restaurants and grocery stores, were forced to close, leading to significant financial losses. For instance, Spiros Johnson, owner of 25th and Clement Produce Market, reported having to discard thousands of dollars worth of perishable inventory. Residents also faced challenges, with many throwing away food from their refrigerators. The outage led to traffic chaos, as traffic signals were non-operational, prompting the San Francisco Department of Emergency Management to advise treating dark signals as four-way stops.

Public Transportation Disruptions

Public transportation services were severely impacted. BART closed several stations, including Powell and Civic Center, while Muni services were disrupted, particularly in the Central Subway. Waymo, the autonomous ride-hailing service, temporarily suspended operations due to stranded vehicles at intersections. By Sunday, most public transport services had resumed, but the effects of the outage lingered.

Official Responses and Statements

San Francisco Mayor Daniel Lurie expressed frustration over the incident, stating, "We need PG&E to do better." He emphasized the need for discussions with PG&E to understand the failure that led to the outage. PG&E spokesperson Melissa Subbotin acknowledged the extensive damage caused by the fire and assured that crews were working diligently to restore power. The utility company has stated that it does not suspect sabotage or malicious activity related to the fire.

Criticism and Calls for Accountability

Local officials, including Supervisors Connie Chan and Alan Wong, have called for a public hearing to investigate the outage's causes and to address recurring issues with PG&E's infrastructure. Wong highlighted the need for improved communication and support for affected residents and businesses. The incident has raised concerns about the reliability of PG&E's services, especially during critical times.

Verbatim Quotes

  • “We need PG&E to do better.” — Daniel Lurie, Mayor of San Francisco
  • “The damage from the fire in our substation was significant and extensive and the repairs and safe restoration will be complex,” — PG&E spokesperson Melissa Subbotin
  • “I have never seen anything like this over the decade I have been here in San Francisco.” — Bilal Mahmood, District 5 Supervisor

Conclusion and Next Steps

As recovery efforts continue, PG&E has opened a resource center in the Richmond District to assist those still without power. The company is expected to provide updates on restoration timelines and address the concerns raised by city officials. The incident underscores the need for a thorough examination of PG&E's infrastructure and emergency response protocols to prevent future outages.