Transformer Fire Causes Outages for 11,000 in San Francisco

12/29/2025

35 4 Full Breakdown

1 of 2

Story summary
  • On December 29, 2025, San Francisco experienced outages affecting over 11,000 Pacific Gas and Electric (PG&E) customers due to a transformer fire and ongoing repairs from a previous substation fire.
  • Outages began around 7:45 p.m.
  • Power was restored by 10:15 p.m.
  • Residents expressed frustration over generator noise.
  • PG&E offered compensation, including bill credits and claims for additional expenses.