HS2's Wendover Green Tunnel Progress: 850 Segments Installed

1/20/2026

36 6 Full Breakdown

1 of 2

Story summary
  • High Speed 2 (HS2) reports progress on the Wendover Green tunnel, 1.1 km long, with completion expected in 2027.
  • Engineers have installed 850 of the 2,740 pre-cast concrete segments.
  • Site challenges include limited equipment space and a low-permeability wall due to the water table.
  • Lessons from previous tunnels have improved logistics and safety, and backfilling processes are being refined to prevent collapse.