Eglinton Crosstown LRT Set to Open Amid Controversy and Criticism

2/8/2026, 4:25:42 AM

Eglinton Crosstown LRT Launch Details

The Eglinton Crosstown Light Rail Transit (LRT) line in Toronto is scheduled to open on Sunday morning, marking the culmination of 15 years of construction and testing. The Toronto Transit Commission (TTC) has emphasized that this will be a "phased opening," with trains operating at reduced speeds and limited hours. The TTC has advised riders to dress warmly and be prepared for potential wait times at stations. The first trains are set to depart around 7:40 a.m., with a frequency of approximately every eight minutes throughout the day.

Background on the Project's Challenges

The Eglinton Crosstown LRT has faced significant delays and cost overruns, with the project now opening five years later than initially planned and at more than double its original cost estimates. Originally proposed in 2007 as part of the "Transit City" initiative by then-Toronto Mayor David Miller, the project underwent significant changes under the previous Liberal provincial governments of Dalton McGuinty and Kathleen Wynne. The oversight was transferred from the TTC to Metrolinx in 2012, and the project was structured as a public-private partnership (P3), which has been criticized for leading to inefficiencies and legal disputes.

Official Responses and Criticism

Ontario Premier Doug Ford has declined to initiate a public inquiry into the Eglinton line's delays, arguing that it would distract Metrolinx from other transit projects, including the $27.2-billion Ontario Line subway. Ford acknowledged the project's difficulties, describing it as a "nightmare," but stated that lessons have already been learned. Opposition MPPs, including Ontario NDP Leader Marit Stiles, have called for an inquiry, criticizing the P3 model as lacking accountability and transparency.

Metrolinx CEO Michael Lindsay has indicated that the agency is adopting a more collaborative approach with contractors for future projects, moving away from the bundled P3 model that characterized the Eglinton line. He noted that the agency is implementing contracts that incentivize timely completion and better manage disruptions for local communities.

Impact on Local Businesses and Communities

The prolonged construction of the Eglinton LRT has had adverse effects on local businesses, with many forced to close during the lengthy build-out. The TTC's decision to conduct a soft launch with reduced hours and speeds reflects ongoing concerns about operational readiness, including issues with automatic emergency brakes on test vehicles, which have since been addressed.

What's Next for the Eglinton Line

As the Eglinton Crosstown LRT begins operations, the TTC plans to gradually increase service levels and improve transit priority measures to enhance efficiency along the route. The opening is seen as a significant milestone for Toronto's transit infrastructure, with city officials, including Mayor Olivia Chow, highlighting its importance as an east-west transit link.

Verbatim Quotes

  • “I’m the first to come out and acknowledge the mistakes, but I’m not going to waste time on [an] inquiry and all the nonsense and tie all these people up.” — Doug Ford, Premier of Ontario
  • “Metrolinx and their P3 public-private-partnership model has been a disaster,” — Marit Stiles, Ontario NDP Leader
  • “This Sunday marks a milestone for the City of Toronto,” — Olivia Chow, Mayor of Toronto