Full Breakdown
Las Vegas Athletics Stadium Construction Progresses Toward 2028 Opening
2/20/2026, 1:01:38 PM
Foundation Work Completed and Construction Timeline
The construction of the new stadium for the Oakland Athletics in Las Vegas is advancing as planned, with the foundation work now complete. Tyler Van Eeckhaut, the project director for contractors Mortenson-McCarthy, confirmed to the Las Vegas Stadium Authority that the project remains on schedule for an opening before the 2028 MLB season. This update aligns with previous communications from December, indicating consistent progress.
Sandy Dean, vice chairman of the Athletics, reported that the team has invested $300 million into the $2 billion, 33,000-seat domed ballpark without yet requesting public financing. The Nevada and Clark County governments have approved up to $380 million in public funds for the project, with the Athletics committed to covering the remaining costs. Dean noted that the team has attracted outside investors to support the stadium's development.
Ticketing Strategy and Community Engagement
As part of their strategy to engage the community, the Athletics plan to sell personal-seat licenses (PCLs) for select high-end seating areas. A's President Marc Badain mentioned that the demand for season tickets is strong, with a deposit list exceeding 20,000. He emphasized that ticket prices would be accessible, with options in the $20 and $30 range aimed at attracting families to the ballpark.
The Athletics are currently in spring training in Mesa, Arizona, but will host two preseason games against the Los Angeles Angels in Las Vegas on March 7-8. Additionally, the team is scheduled to play six regular-season games at Las Vegas Ballpark, the home of their Triple-A affiliate, in June against the Milwaukee Brewers and Colorado Rockies. Tickets for these regular-season games sold out within 24 hours of being offered to season ticket deposit holders.
Official Statements & Responses
The Athletics' leadership expressed optimism about the project's progress. Badain stated, “I feel great about the progress,” highlighting that the construction team has met all deadlines thus far. Dean reiterated the excitement surrounding the project, noting, “It’s good to be here on a day in which we have a lot of tangible progress to report.”
Criticism & Opposition
While the project has garnered significant support, there are concerns regarding the reliance on public funding for a privately-owned sports facility. Critics argue that public funds could be better allocated to community services rather than a stadium that primarily benefits a private entity.
Verbatim Quotes
- “We are excited we continue to be on schedule for the project,” — Tyler Van Eeckhaut, Project Director
- “We have a (season-ticket) deposit list of over 20,000.” — Marc Badain, A's President
- “It's good to be here on a day in which we have a lot of tangible progress to report,” — Sandy Dean, Vice Chairman
The Athletics' new stadium project is poised to reshape the sports landscape in Las Vegas, with ongoing construction and community engagement efforts reflecting a commitment to a successful transition from Oakland.