Dallas Wings' New Practice Facility Delayed Amid Team Transition
2/21/2026, 12:40:30 PM
Overview of the Situation
The Dallas Wings, a professional women's basketball team, are facing delays in the construction of their new practice facility, which is part of a broader transition as they prepare for the 2026 season. The team will continue to practice and play at the University of Texas at Arlington's College Park Center, a venue that has been described as the third-smallest arena in the WNBA.
Timeline of Events
In April 2024, the Dallas City Council approved a 15-year use agreement for the Wings to play at the Kay Bailey Hutchison Convention Center Dallas Memorial Arena. This agreement included plans for a new practice facility, initially expected to be completed by April 2025. However, delays have pushed the groundbreaking ceremony for the facility to September 2025, with a revised completion date now set for spring 2026.
Current Challenges
The Wings' current practice location at College Park Center has presented logistical challenges, particularly during peak usage times. The arena's limited capacity of 7,000 seats has resulted in scheduling conflicts, as the facility is shared with UT Arlington. Head coach Chris Koclanes described the situation as “pandemonium,” highlighting the need for a dedicated space for the team.
Impact on Team Performance
Despite the arrival of top talent, including No. 1 overall pick Paige Bueckers, the Wings finished the 2025 season with a 10-34 record. The team is looking to improve in the upcoming season, with the top pick in the 2026 draft and a potentially advantageous free agency period. The new practice facility is seen as a crucial element in attracting talent and fostering a more conducive training environment.
Official Statements & Responses
City manager Kimberly Bizor Tolbert expressed commitment to the project, stating, “I want to say as we go into the next phase, we want you to hold us accountable... my commitment is that we will deliver this practice facility for you by the spring of 2026.” Wings CEO Greg Bibb echoed this sentiment, referring to the initial agreement and the city's assurances regarding the timeline.
Criticism & Opposition
While the city officials and team management remain optimistic, some critics have raised concerns about the feasibility of the revised timeline. The delays have led to skepticism about whether the facility will indeed be ready by the newly proposed date, especially given the logistical challenges the team currently faces.
What's Next
As the Wings prepare for the 2026 season, they will continue to navigate their current practice arrangements while looking forward to the completion of their new facility. The team is set to play several games at the larger American Airlines Center, which could provide a temporary boost in visibility and fan engagement as they await their dedicated training space.
Verbatim Quotes
- “We’re grateful for the moment, but excited to get our own space, which these players deserve, and we won’t run into issues like this in the future,” — Chris Koclanes, Head Coach
- “I want to say as we go into the next phase, we want you to hold us accountable,” — Kimberly Bizor Tolbert, City Manager