Los Angeles Plans $40 Million Rebuild of Griffith Park Pool

3/24/2026, 12:25:16 AM

Overview of the Project

Los Angeles officials have announced an ambitious plan to rebuild the historic Griffith Park Pool, with a projected cost of $40 million. The project aims to replace the existing pool, which has been closed since 2020 due to significant leakage issues, with a new competition pool, a recreational pool, and a rehabilitated pool house featuring gender-neutral dressing rooms. The completion of the project is targeted for mid-2029.

Historical Context

Originally built in 1927, the Griffith Park Pool has served as a popular destination for swimming lessons and recreational activities. However, it was shut down during the COVID-19 pandemic, and subsequent attempts to refill the pool revealed that it could no longer hold water. The city initially estimated the renovation cost at $28 million, but this figure has since risen due to complications related to the pool's proximity to the freeway and the Los Angeles River.

Project Details

The design, led by the architecture firm Perkins Eastman, includes a 50-meter competition pool and a 25-yard training pool with an ADA-compliant gentle slope. The pool house will maintain its Spanish Colonial Revival exterior while modernizing the interior, which will feature a consolidated gender-neutral changing area with private stalls. The project also aims to incorporate energy-efficient upgrades and comply with modern accessibility laws.

Community Engagement and Concerns

During a recent open house meeting, city officials and designers presented the project to approximately 50 residents, addressing concerns about construction impacts, including potential disruptions to the nearby Los Feliz Nursery School. Community members expressed eagerness for the pool's reopening, emphasizing its importance for local swim lessons.

Criticism and Opposition

The substantial cost of the project has drawn criticism from various quarters. Some residents have labeled the price tag as excessive, with comments on social media questioning the necessity of such spending. Critics have referred to the project as a potential misuse of taxpayer funds, with one resident suggesting it could be a "money laundering scheme." Additionally, some have expressed skepticism about the inclusion of gender-neutral bathrooms, viewing it as a controversial priority.

Official Statements

Stephanie Kingsnorth, principal of Perkins Eastman, stated, “This is something that’s more common for equity and inclusion,” referring to the gender-neutral facilities. Ohaji Abdallah from the Bureau of Engineering noted that the project would compete with other city priorities for funding and emphasized the need for careful planning to minimize disruption during construction.

Timeline and Next Steps

The project is currently in the design development stage, with a timeline that includes six months for construction documents, five months for permits, and 18 months for actual construction. If all goes according to plan, the new Griffith Park Pool complex could be operational by mid-2029, restoring year-round swimming access to the community.

Conflicting Reports & Gaps

While the city has provided a comprehensive overview of the project, some community members remain skeptical about the rising costs and the timeline, questioning whether the ambitious schedule can be met amid competing city budget priorities. The finalization of the construction haul route and its impact on local schools also remains a point of concern.

Verbatim Quotes

  • “The pool is being completely replaced. It leaks like a sieve,” — Stephanie Kingsnorth, Principal, Perkins Eastman
  • “This project will be like all the other money laundering schemes!” — Anonymous Resident
  • “We’re very anxious to have the school come back, so that the kids can learn to swim,” — Marian Dodge, Local Resident