  • The Nuclear Safety and Security Commission (NSSC) approved Korea Hydro & Nuclear Power's (KHNP) restart of Kori-2, offline since April 2023 after its operating permit expired.
  • KHNP said safety measures and improvements enabled Kori-2 to reach criticality and resume operations.
  • The plant can operate through April 2033.
  • KHNP is submitting safety reports for nine other nuclear units with expiring licenses as it plans future operations and decommissioning.