126 Solar Projects Delayed by Regulatory Hurdles, $6M Lost

4/17/2026

49 6 Full Breakdown

1 of 2

Story summary
  • At least 126 solar projects totaling about 20 gigawatts are stalled by regulatory delays that affect agricultural land.
  • Developers face a July 2026 construction deadline, forcing some projects to be abandoned.
  • Alpin Sun has withdrawn from 1,000 megawatts of projects, losing $6 million in investments.
  • RIC Energy North America is advancing its 150 projects on fallow land and New York's Solar for All cannot match federal tax credits.