Imja Lake Early Warning System in Disrepair Raises Flood Risk Concerns in Nepal’s Everest Region

4/25/2026, 10:50:55 AM

Early warning system fails

The UNDP-backed flood warning system installed after Imja lake was drained in 2016 is now largely non-functional: siren towers rust, batteries have been stolen, and satellite data transmission is unreliable, DHM officials say.

Risk-reduction project and rising glacial threats

Imja lake sits at ~5,000 m altitude; in 2016 its depth, then nearly 150 m, was reduced by 3.5 m as part of a $3.5 million risk-reduction project that installed the warning system. Accelerated glacier melt in the Hindu Khush Himalaya has doubled ice-loss rates since 2000, expanding glacial lakes. The Everest region has recorded at least five glacial-lake floods in the past fifty years, threatening six villages and the roughly 60,000 annual tourists.

Government and UNDP perspectives

Senior DHM meteorologist Niraj Pradhananga said the central government has not allocated a maintenance budget and stolen batteries undermine the sirens. Acting DHM director-general Archana Shrestha explained that funds were diverted to upgrade another lake’s system, delaying work on Imja, but new regulations will grant staff more time and resources for remote upkeep. UNDP communications head Monica Upadhyay noted that lessons from Imja have shaped the design of upcoming projects, emphasizing stronger institutional arrangements and dedicated financing.

Community concerns over maintenance

Villagers say promised annual inspections never occurred, leaving sirens inoperable. They warn that the deteriorating infrastructure endangers both the six villages and the 60,000 tourists. Community leaders describe the system as an “eyewash” that fails to provide real protection.

Satellite data dispute

The satellite company asserts no technical problems, while the local service provider has not responded to DHM inquiries, leaving data gaps that impede mobile-alert issuance.

Voices from the field

> “Going by the state of the siren towers, we don't expect to get any flood warning from them even when Imja lake bursts out.” — Ang Nuru Sherpa, chairman, Chaurikharka buffer zone

> “Six villages in the region are vulnerable to floods and so are the more than 60,000 tourists who visit our region every year.” — Tshering Sherpa, CEO, Sagarmatha Pollution Control Committee

> “As a result, we cannot say for sure if the early warning sirens work or they don't.” — Niraj Pradhananga, senior meteorologist, DHM

> “For us in the Khumbu region, it has just been an eyewash.” — Nawang Thome Sherpa, head of local body, Phakding

Plans for expanded safety measures

UNDP secured a $36 million grant to replicate the scheme at four lakes. The revised model will be applied to those sites, with clearer financing and private-sector partnerships. DHM plans to allocate a dedicated maintenance budget, adjust regulations for field staff, and restore Imja’s siren network. Ongoing satellite monitoring and community reporting will track progress.