Story summary
- Maryland invoked the off-ramp provision to terminate Kiewit’s phase-two contract after its price and schedule were deemed unacceptable.
- The project’s cost now ranges $4.3-$5.2 billion versus the original $1.7-$1.9 billion, pushing completion to 2030.
- The Maryland Transportation Authority will host a May industry day to select a new contractor while Kiewit stays on site through year-end.