Trump Approves Pipeline
- President Donald Trump approved a permit for the Bridger Pipeline Expansion on April 30, 2026.
- The 650-mile line will carry up to 550,000 barrels of oil per day from Canada through Montana and Wyoming—about two-thirds the volume of Keystone XL project—and runs on 70% existing corridors and 80% private land.
- Developers plan construction to start in fall 2027 and finish by 2029, pending approvals before Trump’s term ends on Jan. 20, 2029.