Story perspectives
Kevin O'Leary's AI Data Center Approved, Power Demand Stuns
5/7/2026
1 of 3
O'Leary AI Approval
- Box Elder County commissioners unanimously approved billionaire investor Kevin O'Leary's Stratos AI data center project.
- The 40,000-acre site would require up to 9 GW of power, with Phase 1 alone needing 3 GW, nearly Utah’s total current consumption.
- Utah’s Military Installation Development Authority set a 0.5% energy tax, far below the 6% limit, while about 400 protesters filed over 2,500 comments on water and air impacts.
1 / 3