Sweeney Blames Over-Design for $5.5B Surge, Takes Inland Rail Lead
5/7/2026
1 of 1
Story summary
- Sean Sweeney said the new underground stations were over-designed, driving costs up.
- He reported the project cost $5.5 billion, far above the original $3.4 billion estimate.
- Sweeney attributed the rise to inflation, scope changes, pandemic impacts, and a 2018 platform-length extension that roughly doubled station costs.
- He will now lead Australia’s A$30 billion Inland Rail project.