- U.S. utilities charge ratepayers for grid projects before construction via Construction Work In Progress (CWIP) incentives.
- Forty states now have CWIP, double the number from a decade ago.
- Dominion Energy in Virginia collected $2 billion in CWIP fees, adding $11.23 to each bill.
- Critics say CWIP shifts risk to ratepayers while supporters claim it speeds grid upgrades for data-center demand.