Hochul Breaks Ground
- Governor Kathy Hochul and MTA Chair Janno Lieber broke ground on June 8 2026 for the Second Avenue Subway Phase 2.
- The $6.968 billion project will push the Q train to 125th Street and Lexington Avenue, linking 4, 5, 6 lines and Metro-North.
- Contract 2 ($1.97 billion) will begin tunnel-boring in early 2027 with 1.5-million-pound machines at 120th Street.
- Federal funding resumed in April 2026 after a $60 million reimbursement from President Donald Trump, keeping the line on track for 2032 service.