FERC Orders Reforms
  • FERC ordered regional grid operators to propose reforms within 60 days to speed data-center interconnections and protect ratepayers.
  • The orders require operators to justify or revise rules for large energy users, allocate infrastructure costs, and file a 30-day report on generation adequacy.
  • Officials say the measures, urging users to locate near generation, build own supply, or cut peak demand, will protect customers from subsidizing data-center projects that may not occur.