- Meta Platforms contracted 1.6 GW of AI computing capacity from Crusoe for sites in Childress, Texas, and Warrenton, Missouri.
- The two campuses together will supply about 1.6 GW, enough power for roughly 750,000 U.S. homes.
- Crusoe said Microsoft will lease 900 MW at its Texas campus, bringing its contracted capacity near 5 GW.
- Reuters reported that neither Meta nor Crusoe commented on the deal.
- Bloomberg said it could not independently verify the deal.