Grid Upgrade Forces Devon Solar Park Shutdown, £2 M Loss

7/12/2026

23 2 Full Breakdown

1 of 1

Story summary
  • The National Energy System Operator ordered the Derril Water solar park in north Devon to shut for grid upgrades.
  • The shutdown will cost the cooperative’s nearly 10,000 members about £2 million in lost revenue with no compensation expected.
  • The board said the shutdown was enforced without warning despite grid issues since 2023 and upgrades delayed from end-2025 to September.
  • The cooperative financed with £20 million from members and a £22 million bank loan.