Drooid Logo
Back to today’s briefing

Story perspectives

Power line failure knocks 3 GW data centers offline

7/26/2026

38 3 Full Breakdown

1 of 1

Story summary
  • A power line failure near Washington, D.C. knocked more than 3 GW of data centers off the PJM grid, creating voltage spikes.
  • Dominion Energy said a high-voltage transmission component failed, causing the data centers to switch briefly to backup power.
  • PJM recorded a 3.1 GW loss—about 3 % of demand—and restored service in ten minutes.
  • ON.Energy is deploying 3 GW of battery-backed UPS systems to improve resilience.