DOE Announces Hub
- The Department of Energy announced the Paducah hub will include a 1.8-GW AI data center, a 2-GW gas plant and 2.6-GW battery storage.
- Brookfield Asset Management will build and run the data center while NextEra Energy Resources will supply power.
- Construction expects about 8,000 temporary and 600 permanent jobs, with completion by 2031.
- Governor Andy Beshear said his spokesperson had not briefed him on the project as of July 30, 2026.