  • SpaceX announced it will begin removing the 69 turbines at its Southaven, Mississippi site.
  • The agreement with the Mississippi Department of Environmental Quality sets a July 2027 deadline, with removal potentially beginning in August.
  • A 1.2-GW facility scheduled for March 2026 will replace the turbines and power the Colossus 2 data center.
  • The removal follows an April lawsuit by the NAACP and Southern Environmental Law Center alleging 27 turbines operated without a permit.