Texas Gov Orders Audit of Data-Center Grid Connections
8/4/2026
1 of 2
Story summary
- Texas Governor Greg Abbott ordered the Public Utility Commission of Texas (PUCT) and ERCOT to audit data-center projects for grid connection before they can advance in the queue.
- ERCOT is reviewing over 474 GW of requests, with roughly 90 % from data centers.
- The review forces data centers to disclose financial aid, water use and ownership, with projects that fail standards denied access, a step Abbott says protects Texans’ safety.