Texas Gov. Abbott Orders Audit of 474 GW Data-Center Requests
8/5/2026
1 of 4
Abbott Orders Audit
- Texas Governor Greg Abbott ordered Public Utility Commission and ERCOT to audit all data-center projects seeking grid connection on August 3 2026.
- Critics, including Agriculture Commissioner Sid Miller, say the audit is vague and unlikely to curb data-center growth, urging a legislative session or moratorium.
- ERCOT is reviewing 474 gigawatts of data-center interconnection requests, five times Texas’s peak demand.
- Guadalupe County residents sued to block Cloudburst and Palomino Alpha data-centers over water-use concerns.