Magyar Raises Danube
  • Prime Minister Péter Magyar ordered two 80-metre barges sunk on 15 August to raise the Danube level by about 20 centimetres.
  • Engineers are adding a submerged sill that could raise the level by 1 metre, while Paks nuclear plant runs at 485 MW and risks turbine shutdown below –132 cm.
  • Magyar said the emergency costs about 6 billion forints (~$19 million), and Romania shut its Cernavoda reactor on 13 August after Danube levels fell.