Network Rail Reopens Charing Cross After 22-Day Shutdown

8/20/2026

48 6 Full Breakdown

1 of 2

Story summary
  • Network Rail and Southeastern reopened London Charing Cross and Waterloo East after a 22-day summer closure.
  • The £20 million programme replaced nearly two kilometres of 36-year-old track and 16 switches and crossings.
  • Engineers removed 540 tonnes of concrete and installed 2,000 m² of glass-reinforced plastic on all six platforms.
  • The single 22-day closure avoided about 60 weekend closures and reduced overall disruption and delivery costs.