Network Rail Reopens Charing Cross After 22-Day Shutdown
8/20/2026
1 of 2
Story summary
- Network Rail and Southeastern reopened London Charing Cross and Waterloo East after a 22-day summer closure.
- The £20 million programme replaced nearly two kilometres of 36-year-old track and 16 switches and crossings.
- Engineers removed 540 tonnes of concrete and installed 2,000 m² of glass-reinforced plastic on all six platforms.
- The single 22-day closure avoided about 60 weekend closures and reduced overall disruption and delivery costs.