Texas Gov. Greg Abbott Halts New Data-Center Approvals Amid Growing Public Backlash
8/24/2026, 8:58:32 PM
Core Action: Statewide Moratorium and Audit Directive
On June 10, Governor Greg Abbott ordered the Public Utility Commission of Texas (PUCT) and ERCOT to pause all new grid-connection approvals for data-center projects. The pause remains while regulators conduct a “comprehensive verification and audit” of pending proposals. Abbott said the move responds to community opposition and concerns over electricity, water and neighborhood impacts.
Background & Context
Texas markets itself as a hub for artificial-intelligence (AI) investment, offering tax incentives that have drawn dozens of developers. By June 26, the Texas Tribune reported 335 existing data centers and at least 248 projects in the pipeline, making Texas the second-largest state by operational capacity after Virginia. Independent analysis released August 16 estimated roughly 100 GW of planned capacity in Texas—more than the combined pipeline of Virginia and Utah.
Local resistance grew in towns such as Abilene, Sulphur Springs, San Marcos (which adopted a zoning ban on June 16) and Hill County (which briefly imposed a moratorium on June 6). Polling shows strong opposition: a Gallup survey found seven-in-ten Americans oppose nearby data centers; a Reuters/Ipsos poll in June reported only 14 % comfortable living near one; and a University of Texas poll on June 24 indicated 56 % of Texas voters oppose local data-center construction.
Data & Statistics
- ?1,800 projects stalled, representing about 474 GW of interconnection requests—over five times ERCOT’s all-time peak demand.
- Abbott’s office estimates ?90 % of those requests are from data-center developers.
- Fewer than 10 % of data centers have complied with state reporting on power and water usage.
- Companies that have pledged compliance include Power House Data Centers, CoreWeave, Emergent Data Centers, and a coalition of more than 40 tech firms (e.g., OpenAI, Anthropic, Amazon, Google, Microsoft, Meta).
Official Statements & Responses
Abbott said the agency’s goal is a “December 10 filing” for the audit report and noted the study will not be completed by April 9, 2027.
Criticism & Opposition
Critics argue the pause may delay economic benefits, while Abbott maintains it protects Texans from grid strain and water shortages.
On-the-Ground Reports
Residents in Abilene, Sulphur Springs and other rural locales have attended planning meetings, filed petitions and staged protests. Local officials in San Marcos and Hill County have taken steps to restrict or ban data-center development, citing water and energy concerns.
Conflicting Reports & Gaps
Independent estimates of Texas’s data-center pipeline differ. Apollo Global Management’s chief economist cited ?100 GW of planned capacity, while ERCOT’s interconnection queue reflects ?474 GW of raw requests—many of which may be speculative or duplicated. The discrepancy highlights uncertainty about how much of the proposed capacity will materialize.
Verbatim Quotes
- “They basically dug their own grave for the problem that’s been caused for them, and that’s why they got the backlash they deserve,” — Greg Abbott
- “Our goal is to head toward a December 10 filing,” — Chad Seely
What’s Next
- ERCOT plans to issue RFIs to large-load developers by the end of the month, targeting an audit filing by December 10.
- The comprehensive study will not be finished by April 9, 2027, leaving the final timeline open.
- Abbott gave regulators until July 17 to report on actions taken under current law and to propose legislative changes.
The audit’s outcome and subsequent regulatory actions will shape Texas’s role in the national AI and data-center landscape, influencing both the state’s economy and residents’ daily lives.