  • Global Energy Monitor reported that U.S. gas-powered projects for data centers more than doubled by mid-2026.
  • The pipeline grew from 4 GW in early 2024 to 97 GW by end 2025.
  • By mid-2026, the pipeline reached over 189 GW of gas capacity.
  • Data center builders increasingly use behind-the-meter gas plants to avoid grid delays.
  • Many new gas plants use inefficient turbines, raising emissions comparable to those of small countries.