Network Rail to reopen Haywards Heath–Lewes line September 1
8/29/2026
1 of 2
Story summary
- Network Rail engineers will reopen the Haywards Heath-Lewes line on 1 September.
- Engineers have completed over 80% of the recovery work following the 13 August derailment.
- Teams rebuilt the embankment, installed replacement track and repositioned signalling equipment.
- Over 5,000 work hours were logged and 9,000 tonnes of aggregate arrived via 250 tipper trucks.
- Engineers will renew 500 metres of track and replace 850 sleepers on a 160-metre embankment.