Network Rail to reopen Haywards Heath–Lewes line September 1

8/29/2026

27 4 Full Breakdown

1 of 2

Story summary
  • Network Rail engineers will reopen the Haywards Heath-Lewes line on 1 September.
  • Engineers have completed over 80% of the recovery work following the 13 August derailment.
  • Teams rebuilt the embankment, installed replacement track and repositioned signalling equipment.
  • Over 5,000 work hours were logged and 9,000 tonnes of aggregate arrived via 250 tipper trucks.
  • Engineers will renew 500 metres of track and replace 850 sleepers on a 160-metre embankment.