Full Breakdown
Vineland AI Data Center Faces Noise Lawsuit and Unpermitted Generator Allegations
8/29/2026, 1:01:55 AM
Core Event – Community Lawsuit Over Noise and Unpermitted Power Sources
Residents of Vineland, New Jersey, have filed a federal class-action lawsuit alleging that the 350 MW DataOne artificial-intelligence data center creates a nuisance with sound that reaches up to one mile from the site. The complaint also claims the facility is operating dozens of gas-powered generators without the required air-emission permits, a possible violation of federal law.
Background & Context – Rapid AI Expansion and Lapsed Noise Regulation
DataOne broke ground in 2025 on a 2.5-million-square-foot campus that will provide AI computing power to Microsoft under a $17 billion contract with Dutch firm Nebius. The “bring your own power” model—building on-site gas generators—has become common among large AI facilities, with research firm Cleanview estimating nearly 60 U.S. data centers pursuing similar plans.
Noise-pollution oversight in the United States waned after the EPA’s regional noise centers were defunded in 1982. Only the Rutgers University Noise Technical Assistance Center remains operational in New Jersey, and its director has called for updated permissible sound levels.
Data & Statistics – Scale, Generators, and Complaint Volume
- The partially built campus occupies roughly 2.5 million sq ft (about 25 times the size of a typical 100,000 sq ft data center).
- Thermal-drone footage captured at least 45 of the site’s 62 generators running simultaneously; another source noted 25 generators active in late June.
- Residents have reported the humming noise “constantly” and have contacted the county health department about 20 times.
Official Statements & Responses – Company, Regulators, and Partners
DataOne’s spokesperson, Naomi Race, said the company has added a northern wall, adjusted construction timing, and hired a sound-mitigation specialist to reduce noise.
A New Jersey Department of Environmental Protection (NJDEP) spokesperson confirmed that no permits have been issued for the generators and that the agency is still conducting a “full compliance determination.”
The EPA indicated that state agencies, not the federal EPA, hold authority over air-permit decisions for the site.
Nebius has not issued a public comment on the allegations.
Criticism & Opposition – Residents, Advocacy Groups, and Lawmakers
Former EPA air-enforcement chief Bruce Buckheit argues the unpermitted generators “violate federal law” and should be shut down with fines for “illegal emissions.”
Quiet Communities Inc., led by President Jamie Banks, emphasizes that noise is the “forgotten stepchild” of data-center impacts, adding that low-frequency sound can travel long distances and affect homes.
U.S. Senator Bernie Sanders (I-VT) and Representative Alexandria Ocasio-Cortez (D-NY) have proposed a moratorium on new data-center construction, citing community health and environmental concerns.
Local resident Andrew Groetsch described the sound as constant, while his partner Stevi Groetsch asked, “If you don’t follow one rule, what makes us have any reason to believe that you would then follow others?”
On-the-Ground Reports – Residents’ Experiences
Michael Gentile, another plaintiff, reported feeling vibration on his porch and having called the health department roughly 20 times without resolution. Tallis West noted that “outside is not even enjoyable to sit outside because of the noise sometimes.”
Conflicting Reports & Gaps – Generator Counts and Permit Status
Sources differ on how many generators were operating at the time of observation: one investigation documented at least 45 of 62 units active, while another report cited 25 generators in late June. The NJDEP has not yet issued permits nor confirmed any pending applications, leaving the legal status of the generators uncertain.