NJ DEP Investigates 45 Unpermitted Generators at AI Center

8/29/2026

36 3 Full Breakdown

1 of 1

Story summary
  • DataOne operates dozens of natural-gas generators at its Vineland, New Jersey AI data center without permits.
  • New Jersey DEP launched an investigation after Floodlight’s thermal-drone footage showed 45 unpermitted generators.
  • Bruce Buckheit, former EPA air chief, said the emissions likely violate federal law and threaten public health.
  • Sen. Bernie Sanders (I-VT) and Rep. Alexandria Ocasio-Cortez (D-NY) urged a moratorium on new data centers.