Full Breakdown
High Court Injunction vs. Ongoing Work at Sheering Mill Lane
8/30/2026, 8:05:17 PM
Unauthorized Development and Legal Action
Builders began major earth-moving on a flood-plain field off Sheering Mill Lane in Sawbridgeworth on the afternoon of August 28. Residents described the work as “unauthorised” and lacking planning permission. East Hertfordshire District Council (EHC) issued a Temporary Stop Notice on August 29, which was ignored, prompting the council to seek an emergency High Court injunction that was served later that night. The injunction, effective from August 29, temporarily bans further development, placement of caravans, and occupation of the plot.
Background & Context
The site lies on a Green Belt flood plain, a protected area intended to prevent urban sprawl and preserve natural habitats. Similar illegal works have occurred on green-belt land elsewhere in the region during Bank Holiday weekends, highlighting a pattern of “land grabs” that exploit the holiday lull.
Timeline
- August 28 – Heavy machinery and delivery trucks arrive, beginning excavation.
- August 29 – EHC serves a Temporary Stop Notice; the council applies for an emergency injunction.
- August 30 – Builders continue work despite the High Court injunction.
- September 15 – A High Court hearing is set to consider the council’s application.
Data & Statistics
- Up to 400 local residents gathered to protest, according to a BBC reporter.
- Vehicles exceeding the 3-ton bridge limit were observed delivering “tons of hardcore,” timber, drainage pipes, and fencing.
- The field is frequented by muntjacs and other wildlife and functions as a flood-plain that residents say protects nearby homes.
Official Statements & Responses
Josh Dean, Labour MP for Hertford and Stortford, warned that the land would be “decimated and replaced with concrete” if the development proceeds.
Criticism & Opposition
On-the-Ground Reports
Eyewitnesses described diggers and JCBs tearing the wetland apart from early morning, with trucks unloading material continuously. Residents blocked the bridge to impede deliveries, while police made brief appearances and monitored the situation without intervening. A BBC reporter observed that work continued on August 30 despite the injunction.
Conflicting Reports & Gaps
The council’s injunction is intended to halt further development, yet construction persisted after the order was served. Police have acknowledged awareness of the dispute but have not clarified the legal limits of their intervention, leaving uncertainty about enforcement effectiveness.
Why It Matters
The incident pits environmental protection and flood-risk mitigation against unregulated development on protected green-belt land. It raises questions about the capacity of local authorities to enforce planning law during holiday periods and the role of civil-law mechanisms—such as temporary stop notices and injunctions—in safeguarding community assets.
What’s Next
A High Court hearing is scheduled for September 15 to determine whether the injunction will be upheld and what further enforcement actions may follow.
Verbatim Quotes
- “East Herts issued the Temporary Stop Notice this morning. This has been ignored, so the council is working on an emergency application for an injunction to prevent occupation of the site. Legal and enforcement officers at the council are gathering the necessary information and hope that a temporary injunction can be issued today.” — The Indie
- “Each step has to be evidenced and lawfully served. It’s slower than residents want, but it’s what makes sure the eviction, when it happens, actually sticks.” — The Indie