Contractors to Pay for Queen Mary Hospital Lift Defects

9/9/2026

28 5 Full Breakdown

1 of 1

Story summary
  • Secretary Bernadette Linn said contractors will bear costs for faulty lifts at Queen Mary Hospital.
  • Lift defects left 24 of 28 elevators unfit, delaying block commissioning by up to a year.
  • Paul Y-Able joint venture and subcontractor Anlev Elex Elevator are liable for remedial work.
  • Authorities will seek compensation while keeping HK$13.5 billion project spending unchanged.
  • Contractors claim fixes by Q4 2026, prompting the Development Bureau to review inspection procedures.