- Secretary Bernadette Linn said contractors will bear costs for faulty lifts at Queen Mary Hospital.
- Lift defects left 24 of 28 elevators unfit, delaying block commissioning by up to a year.
- Paul Y-Able joint venture and subcontractor Anlev Elex Elevator are liable for remedial work.
- Authorities will seek compensation while keeping HK$13.5 billion project spending unchanged.
- Contractors claim fixes by Q4 2026, prompting the Development Bureau to review inspection procedures.