Jerusalem Court Clears Way for Contested E1 Housing Tender

9/9/2026, 7:10:19 AM

Court Allows E1 Tender to Proceed

On Tuesday the Jerusalem District Court ruled that a tender for 1,234 homes in the E1 zone—an undeveloped strip between Jerusalem and the settlement of Ma’aleh Adumim—may move forward. The decision does not constitute final approval of the underlying construction plans, leaving the three pending petitions able to halt or modify the project. Contractors must submit bids by October 19; the court may still intervene before any physical work begins.

Legal Challenge and Petitions

Palestinian residents, joined by the NGOs Ir Amim, Bimkom – Planners for Planning Rights, and Peace Now, filed a request to freeze the tender, arguing that advancing it would draw private developers and make it increasingly difficult to stop (allegation). The petitioners contend the broader E1 scheme would eventually force nearby Palestinian and Bedouin communities from their homes and trigger demolitions (allegation). They also claim the government rushed the tender—published on August 18 without prior notice—to create “facts on the ground” before the October 27 election (attributed claim).

Government Position and Official Responses

Finance Minister Bezalel Smotrich, who oversees civilian affairs in the West Bank, presented the project as a means to prevent the establishment of a Palestinian state (attributed claim). The state admitted that its lawyers had not been alerted before the tender’s publication because of an internal error, but argued that the informal promise of notice did not justify halting the process (attributed claim). The government also pledged to notify the court seven days before any physical development if the petitions remain unresolved (established fact).

Opposition from Palestinian Groups and International Critics

British Foreign Secretary Ed Miliband accused settlers of carrying out ethnic cleansing in parts of the West Bank, saying the Israeli government often turns a blind eye and that some officials have supported forced displacement, citing E1 as a project that threatens a two-state solution (attributed claim).

Timeline of Key Developments

  • August 18 – Tender for 1,234 E1 homes published without advance notice.
  • October 19 – Deadline for contractors to submit bids.
  • October 27 – Scheduled Israeli election, cited by petitioners as a motive for acceleration.
  • June (year unspecified) – Court ordered the state to answer petitions in detail.
  • October & November 2025 – Court previously refused to freeze the plans.

The tender proceeds amid ongoing legal scrutiny, with the final court ruling poised to determine whether the disputed housing project can be realized.