Storm Damage Puts Toronto’s Rogers Stadium Concert at Risk

9/9/2026, 10:48:58 PM

Storm Damage Threatens Rogers Stadium

A severe rain-and-hail event described by city officials as a “100-year storm” struck Toronto last week, causing extensive damage to the temporary Rogers Stadium. Inspectors reported that sections of the north grandstands collapsed and bleachers were scattered across the field, prompting an unsafe-building order from municipal authorities.

City Actions and Engineering Report

The City of Toronto required Live Nation, the stadium’s operator, to retain an engineer, assess the damage, and submit a detailed report outlining remedial measures and a repair schedule. The city confirmed receipt of the engineering report and said it is under review. Officials emphasized that any reconstruction will need a building permit and that the city will continue to work with the venue owner throughout the remediation process.

Live Nation’s Obligations and Timeline

Live Nation met the early-September deadline to deliver its engineering findings. The municipal order also obliges the promoter to follow the engineer’s recommendations and provide an update on progress by a subsequent early-September date. The company has previously stated that it remains engaged with the city and is proceeding with the required inspections and repairs.

Potential Impact on the AC/DC Concert

The damage and ensuing regulatory steps have placed the final show of the season— a sold-out AC/DC performance scheduled for mid-September— in jeopardy. If the required repairs and permitting are not completed in time, the concert could be canceled, though city officials have not ruled out the possibility of proceeding should the venue be deemed safe.

Next Steps

Toronto officials will continue to evaluate the engineering report and monitor repair work. Live Nation must obtain the necessary building permit and demonstrate that the stadium meets safety standards before the concert can go ahead. The outcome will be decided in the coming weeks as the city and promoter work through the remediation process.