North Carolina Utilities Commission Denies Duke’s $584 Million Turbine Request
By Drooid · · How we work
1 of 1
Story summary
- The North Carolina Utilities Commission denied Duke Energy’s $584 million natural-gas turbine request.
- Regulators said Duke failed to show the project’s necessity or customer cost protection.
- The proposed turbine would generate about 255 megawatts by 2030 at the Sherwood H. Smith Complex.
- One commissioner dissented, arguing the turbine is needed for grid reliability as demand grows.
- Regulators told Duke to detail financing, data-center demand share, and cheaper alternatives if it reapplies.