North Carolina Utilities Commission Denies Duke’s $584 Million Turbine Request

By Drooid · · How we work

10 2 Full Breakdown

1 of 1

Story summary
  • The North Carolina Utilities Commission denied Duke Energy’s $584 million natural-gas turbine request.
  • Regulators said Duke failed to show the project’s necessity or customer cost protection.
  • The proposed turbine would generate about 255 megawatts by 2030 at the Sherwood H. Smith Complex.
  • One commissioner dissented, arguing the turbine is needed for grid reliability as demand grows.
  • Regulators told Duke to detail financing, data-center demand share, and cheaper alternatives if it reapplies.