- Governor Greg Abbott ordered the Texas Commission on Environmental Quality to halt all data-center permits pending an audit.
- ERCOT and the Texas Water Development Board will audit electricity, water use and tax incentives for the projects.
- Nearly 470 GW of data-center projects—over five times Texas’s peak demand—await grid connection.
- The pause could reduce data-center revenue by up to $8 billion by Q1 2027.
- TCEQ must report compliance by Oct. 19.