Texas Governor Halts Data Center Permits Pending Grid and Water Audit

By Drooid · · How we work

Core Event

On September 21, 2026, Governor Greg Abbott directed the Texas Commission on Environmental Quality (TCEQ) to stop issuing all air and water permits for new data-center projects. The pause remains until the Electric Reliability Council of Texas (ERCOT) and the Texas Water Development Board (TWDB) finish an audit of the facilities’ electricity and water demands and community impacts.

Background & Context

The AI and cloud-computing boom has made Texas a fast-growing data-center hub. In August, Abbott ordered ERCOT, the Public Utility Commission of Texas (PUCT), and the TWDB to audit data-center requests for grid interconnection, freezing new connections for facilities seeking at least 75 MW of power. The September directive expands the moratorium to all environmental approvals, covering projects that would build on-site power plants or seek water permits.

Data & Statistics

  • Pending load: ERCOT reported ?474 GW of data-center interconnection requests, over five times the state’s historic peak demand.
  • Project counts: The Dallas Express survey lists 461 projects under review, with 247 seeking >=75 MW and 214 seeking 25-75 MW.
  • Water-use response: About 28 % of data centers have responded to the state-mandated water-usage survey.
  • Geographic scope: ERCOT covers most of the state; portions of East Texas, the Panhandle, and El Paso fall under PUCT authority.

Official Statements & Responses

TCEQ spokesperson Ryan Vise confirmed the agency has paused all air and water permits related to data-center infrastructure while ERCOT conducts its audit, which ERCOT expects to finish by December. The audit questionnaire is public, but individual responses will remain confidential. Agencies plan to publish a consolidated report by December 10.

Conflicting Reports & Gaps

Sources differ on the total gigawatt figure: the Jerusalem Post cites “more than 470 GW,” Bloomberg notes “approximately 474 GW,” while the Dallas Express focuses on 461 specific projects. It is unclear whether these totals represent firm commitments or merely requests, and ERCOT officials warn many projects may never be built or could request less power than initially stated.

The permit pause’s scope also varies. Some outlets report that Abbott’s order applies to all data-center permits, including on-site power generation, while others note ERCOT can only halt grid connections for facilities requesting >=75 MW. Clarification from PUCT or TWDB on treatment of non-ERCOT-covered projects is absent.

Verbatim Quotes

  • “Simply put, Texans must come first,” — Greg Abbott
  • “Our top priority is to protect Texans’ safety and quality of life,” — Greg Abbott

What’s Next

  • October 12 (scheduled): Developers must submit complete responses to ERCOT’s information request, including notarized attestations.
  • December 10 (scheduled): ERCOT and the PUCT will release the audit’s findings.
  • TCEQ must report its compliance with the governor’s directive by mid-October.

The audit’s outcome will determine whether pending data-center projects can proceed with environmental permits and grid interconnection, shaping Texas’s role in the national AI and cloud-computing infrastructure.