Oracle Issues Force-Majeure
  • Oracle Corp. sent a force-majeure notice to Blue Owl’s Stack Infrastructure for Project Jupiter.
  • Oracle seeks to defer lease payments if the project does not start operations by 2028.
  • Oracle stock fell about 5%, and shares of Blue Owl and Bloom Energy also dropped.
  • Project Jupiter is financed by an $18 billion loan from roughly 20 banks, trading at 89-91 cents.