People Mover Delayed to January 6 With $3.34B Cost

By Drooid · · How we work

1 1 Full Breakdown

1 of 1

Story summary
  • Los Angeles World Airports says the People Mover project is delayed, now targeting a January 6 opening.
  • The project's cost has risen to $3.34 billion, $880 million over the original $1.9 billion budget.
  • LINXS secured a lender agreement extending the testing deadline to Dec. 8, 2026 to avoid technical default.
  • The train must complete 30 consecutive days of successful testing before carrying passengers.
  • LINXS spokesperson said the project is about 99% complete, focusing on remaining testing.