Heathrow’s Third Runway Delayed to 2039 Amid Planning Uncertainty

By Drooid · · How we work

Core Event: Revised Opening Timeline

Heathrow Airport has told the UK government that the target to have a third runway operational by 2035 is no longer achievable. After securing planning permission by 2029, the runway could open within a decade of approval, moving the earliest realistic opening to 2039.

Background & Context

The 2035 deadline was set in early 2025 when then-Chancellor Rachel Reeves announced a £33 billion investment for a new runway as part of a £49 billion modernisation plan. The plan was backed by Prime Minister Andy Burnham. Subsequent Treasury changes saw John Healey replace Reeves as chancellor.

Data & Statistics

  • Runway cost: £33 billion (runway-specific) within a total £49 billion airport investment.
  • Flight capacity: Current annual limit of 480,000 flights could rise to 720,000, roughly 2,000 flights per day.
  • Infrastructure impacts: Demolition of hundreds of homes, diversion of rivers, and a tunnel for the M25 between junctions 14 and 15.

*Correction 26 September:* An earlier version listed the runway cost as £49 billion; the figure has been corrected to show £49 billion is the total airport investment, with £33 billion allocated to the runway.

Official Statements & Responses

The Department for Transport (DfT) said there is no live planning application and it will continue to work “at pace” with promoters to establish a framework for a future application.

Heathrow’s spokesperson said “ambitious targets were set” and that securing planning permission by 2029 remains the focus, with the runway expected to open within ten years of approval.

Transport Secretary Heidi Alexander noted climate advisers presented “one view” on meeting net-zero obligations but argued “more than one pathway” exists to reconcile expansion with climate goals.

The Climate Change Committee warned the runway is not currently compatible with the UK’s net-zero target, suggesting any carbon impact would need to be offset elsewhere.

Criticism & Opposition

London Mayor Sadiq Khan opposes the project, citing noise, air-pollution and climate concerns. Environmental groups echo these worries, arguing the expansion would increase emissions and affect public health.

Nigel Farage, leader of Reform UK, called the delay a sign of “third-world decline,” contrasting the UK’s progress with China’s rapid airport construction.

Conflicting Reports & Gaps

The main discrepancy concerns the total cost. Early reports cited a £49 billion runway cost; later corrections show the runway itself costs £33 billion within a £49 billion overall investment. No other substantive gaps appear in the sources.

Verbatim Quotes

  • “There is currently no live planning application for a third runway, and we cannot comment on ongoing consultation processes or prejudice them in a way that will only delay progress.” — DfT spokesperson
  • “It’s right that ambitious targets were set; the sooner expansion begins, the sooner the whole UK will benefit. Our focus has always been to secure planning permission by 2029.” — Heathrow spokesperson
  • “This is a national project, 100 per cent privately financed, which will support growth today and secure the UK’s position in the global economy once the runway opens.” — Climate Change Committee