Oracle Force Majeure Delays Project Jupiter Pipeline to 2027
By Drooid · · How we work
1 of 1
Story summary
- Oracle issued a force majeure notice on Project Jupiter, the New Mexico data-center campus.
- Oracle reaffirmed its commitment to the campus and its fuel-cell contract with Bloom Energy.
- Bloom Energy confirmed the 2.4 GW fuel-cell contract remains binding and on schedule.
- The campus’s natural-gas pipeline now expects in-service on February 1 2027, six months later than planned.
- Bloom Energy shares rose 8% to €254.50 as investors saw the notice as a permitting issue.