Core Event: Government Introduces Tougher Datacentre Rules After Rising Opposition

The Victorian Labor government announced a “sustainable datacentre action plan” that bans new facilities within 150 metres of homes and schools, mandates renewable-energy use, and requires formal community consultation. The rules apply only to future projects; approvals already lodged are exempt. The shift follows months of meetings with AI and datacentre executives, a change of premier in July, and protests from residents in Melbourne’s western suburbs.

Background & Context

In early 2026 the state pursued a “datacentre capital” strategy, highlighted by a March dinner at Government House where Premier Jacinta Allan and Minister Danny Pearson met AI leaders and datacentre executives. By mid-year, community concerns over noise, diesel-generator emissions, and fire risk grew, prompting a July cabinet rethink and the eventual approval of stricter rules.

Data & Statistics

  • About 50 datacentres operate in Victoria, with 18 more planned.
  • The NextDC “M3” expansion in West Footscray would double a facility on a 10-hectare site just 15 metres from homes.
  • A July survey of 1,000 Australians found 83 percent would refuse to buy a home near a datacentre without a discount, estimating a loss of up to $35,000 per property.
  • The sector reported $5.8 billion in capital expenditure last year.

Official Statements & Responses

  • Minister for Jobs Melissa Horne wrote to NextDC CEO Craig Scroggie, saying she would not support the fast-track application for the M3 expansion.
  • Data Centres Australia chief executive Belinda Dennett warned the rules could drive investment to other states, a claim rebutted by Artificial-Intelligence Minister Anthony Carbines, who said there is no evidence of capital leaving Victoria.
  • Queensland Premier David Crisafulli announced a $31.9 billion AI-datacentre deal with Anthropic, suggesting other states are capitalising on the sector.

Criticism & Opposition

Community activist Sean Brown of Citizens of Tottenham described early government replies as “polite” but uncaring, noting a shift to direct ministerial engagement in July. Local MP Katie Hall, backed by the Greens, highlighted the proximity of the M3 site to residences and urged a slowdown. Greens Senator Sarah Hanson-Young argued that only trillion-dollar AI firms benefit and called for compensation for affected residents. Hume City Council Mayor Carly Moore echoed concerns about the scientific basis of the buffer.

Verbatim Quotes

  • “I do not believe that it would be appropriate for me to lend my support to the application and nor do I wish to,” — Melissa Horne
  • “It felt like they didn’t care,” — Sean Brown
  • “Other states have seen the opportunity, and they are lining up for it,” — Belinda Dennett
  • “There is no evidence from Data Centres Australia that any investment is leaving our state,” — Carbines

Conflicting Reports & Gaps

No independent data on capital movement has been presented, leaving the actual impact on future investment unclear.

What’s Next

  • Queensland’s $31.9 billion AI-datacentre agreement with Anthropic is expected to proceed, potentially shifting some development away from Victoria.
  • The Senate inquiry into AI and datacentre impacts continues, with testimony from developers such as Phil Galloway of Syncline Energy, who defended a proposed 350-hectare AI hub while acknowledging shortcomings in community engagement.
  • Victoria’s new regulations will be tested as pending applications, including the NextDC expansion, move toward final approval under the revised framework.