Fed IG Finds $2.4B Renovation Mismanaged, Costs Soared

By Drooid · · How we work

6 1 Full Breakdown

1 of 1

Story summary
  • The Federal Reserve (Fed)’s inspector general found the central bank broadly mismanaged the $2.4 billion renovation, but reported no criminal violations.
  • The Board never secured a cost estimate or a maximum overall cost for the renovation.
  • Renovation costs climbed from a $921 million estimate in Feb 2020 to $2.018 billion by Dec 2024.
  • Completion is now projected for Dec 2027, later than the original mid-2024 target.