USS Harry S. Truman Begins $5.1 B Midlife Refueling and Complex Overhaul

By Drooid · · How we work

Core Event: $5.1 B Fixed-Ceiling Incentive Contract Awarded

On September 29 2026, Huntington Ingalls Industries (HII) – Newport News Shipbuilding received a $5,099,973,132 fixed-ceiling incentive contract to execute the Refueling and Complex Overhaul (RCOH) of the nuclear-powered aircraft carrier USS Harry S. Truman (CVN-75). Options could raise the total to $5,183,380,744. The overhaul is scheduled to conclude in November 2031, extending the carrier’s service life by roughly 25 years.

Background & Context

USS Harry S. Truman, commissioned on July 25 1998, is the eighth of ten Nimitz-class carriers to undergo an RCOH, a once-in-a-carrier-lifetime process that replaces the cores of its two Westinghouse A4W pressurized-water reactors and modernizes propulsion, combat and aviation systems. The ship arrived at the Newport News yard on September 30 after a 251-day deployment that included more than 13,000 sorties against Houthi forces in Yemen and a collision with the Panamanian-flagged cargo ship Besiktas-M near the Suez Canal. The collision caused damage to a starboard sponson and bulkheads but no injuries or reactor impact.

The Navy’s Portfolio Acquisition Executive Maritime (PAE Maritime), created in March 2024 to centralize surface-ship acquisition, oversaw the award. The contract’s Fixed-Ceiling Incentive structure is intended to share risk and motivate schedule performance.

Data & Statistics

Data & Statistics
ItemFigure
Contract base value$5,099,973,132
Maximum contract with options$5,183,380,744
Expected completionNovember 2031
Portion of carrier’s life-cycle maintenance~33 %
Reactor typeTwo Westinghouse A4W nuclear reactors
Displacement / length103,900 tons; 1,092 ft
Crew complement>3,500 personnel plus up to 90 aircraft
Prior RCOH duration (USS George Washington)2,117 days (?5 years 9 months)

Criticism & Opposition

Sean Spoonts, former Navy aviation anti-submarine warfare operator and defense analyst, warned that the timing “could not be worse” given the ongoing Iran conflict and suggested additional turbine replacements could extend the overhaul.

Conflicting Reports & Gaps

  • Timeline expectations differ: Forbes cites a three-to-four-year duration, while STRIPES emphasizes a three-year work period ending November 2031.
  • Cost ceiling figures vary slightly: Forbes mentions a $5.1 billion contract, whereas other sources detail the base award and option amounts that could bring the total to $5.183 billion.

Verbatim Quotes

  • “We’ve taken a proactive approach, from ordering long lead-time materials to conducting thousands of inspections and preliminary work, to ensure the RCOH of USS Harry S. Truman is successful,” — Bryan Caccavale, NNS vice president of program management
  • “This award is the latest example of how we are leveraging innovative contracting approaches to drive improved outcomes,” — Rear Admiral Casey Moton

What’s Next

  • November 2031: Planned completion of the RCOH and redelivery of Truman to the fleet.
  • 2027: Preliminary acceptance of the future USS John F. Kennedy (CVN-79), which will join the fleet as older carriers retire.
  • Ongoing monitoring of crew mental-health resources, following nine suicides reported during the earlier USS George Washington RCOH, will continue throughout Truman’s overhaul.