Park Service Refills Lincoln Memorial Pool After Liner Failures

By Drooid · · How we work

24 2 Full Breakdown

1 of 1

Story summary
  • U.S. National Park Service began refilling the Lincoln Memorial Reflecting Pool on Oct. 12, 2026.
  • Renovation costs have risen above $16 million, far above the original $2 million estimate.
  • Inspection found the new liner failed at least 85 locations, with blistering and cracks.
  • Atlantic Industrial Coatings completed warranty repairs on Oct. 2, 2026 after receiving a no-bid contract.
  • FBI agents are assisting U.S. Park Police in investigating the damage with laser-scanning equipment.